Earned value management: Difference between revisions

From formulasearchengine
Jump to navigation Jump to search
en>Kuru
rmv odd inline link to some blog
 
en>Ev2geny
Line 1: Line 1:
== . Now in the third year Longchamp Pliage ==
'''Earned value management''' ('''EVM'''), or '''Earned value project/performance management''' ('''EVPM''') is a [[project management]] technique for measuring project performance and progress in an objective manner.


Well said! Surely its as much as Justin's fans to say whether they are losing curiosity about him and not the people who don't like him anyway. I saw the footage from the paparazzi incident too and he was verbally abused by the so called photographers. I'm sure he'd had more of that and couldn't stand it any more. <br><br>Before the onair experience [http://www.ceremonieswithsoul.com.au/install/footer.asp?id=13-Longchamp-Pliage Longchamp Pliage] a producer may wish to talk to you to see if you will create a good guest or not. If they want to proceed they'll generate a time for the actual on air interview. When they aren't interested they will usually state that they'll get back to you and you will never hear from them again. <br><br>The dissociative process allows teenagers to detachfrom their own bodies, their environmentand their behavior. As the body isinjured, they immediately experiencepositive effects. The negative thoughtsand feelings are forgotten along with a fleetingsense of control is reclaimed. <br><br>Medicaid Along with other Health $110 BillionThe original funding levels proposed by Cantor and also the GOP leadership would turn the entitlement program for America's poor into little more than a block grant program, Democrats claimed throughout the 2011 debt ceiling talks. Under such a program, they argued that states would then drop more and more people from enrollment and scale back on health benefits. In fiscal year 2009, over 62 million Americans  many of these children  depended on Medicaid for their health care. <br><br>Each power plant has reduced kerosene consumption by 42,000 litres and diesel consumption by 18,000 litres in the villages it covers. As the biomassbased power plants are nonpolluting, it is estimated that from 2007 to August 2010 HPS helps cut carbon dioxide emission by 50,000 tonnes. The company has been shortlisted for the Ashden Award for sustainable [http://www.ceremonieswithsoul.com.au/install/footer.asp?id=13-Longchamp-Pliage Longchamp Pliage] energy.. <br><br>He was only shopping price. What a gentleman. One could only imagine what he spent to make her selfdefense toolbox complete. The Fed didn tell anyone which banks were in danger so deep they required a combined $1.2 [http://www.goldcoastbridgeclub.com/results/unprocessed/newsletter.asp?id=6-Louboutin-Pigalle-Spikes Louboutin Pigalle Spikes] trillion on Dec. 5, 2008, their single neediest day. Bankers didn point out that they took tens of vast amounts of dollars in emergency loans simultaneously they were assuring investors their firms were healthy. <br><br>All of this talk  but how can we change social norms? Changing perceptions starts by inspiring new generations of young children and girls  helping them shape their thoughts about who or what a scientist is really. We are taking a small step towards accomplishing this at this year's Soapbox Science event, on London's Southbank on 16 July 16(123pm). Now in its third year, Soapbox Science gives the [http://www.marriagecelebrantjillemerton.com.au/scripts/search.asp?page=49-Lv-Sydney Lv Sydney] public the chance to hear firsthand from UK's top female scientists.<ul>
== Overview ==
 
Earned value management is a project management technique for measuring project performance and progress. It has the ability to combine measurements of:
  <li>[http://www.vc1000.com/news/html/?83497.html http://www.vc1000.com/news/html/?83497.html]</li>
* Scope
 
* Schedule, and
  <li>[http://111.11.181.205:8082/news/html/?55390.html http://111.11.181.205:8082/news/html/?55390.html]</li>
* Costs
 
In a single integrated system, Earned Value Management is able to provide accurate forecasts of project performance problems, which is an important contribution for project management.
  <li>[http://enseignement-lsf.com/spip.php?article64#forum18145805 http://enseignement-lsf.com/spip.php?article64#forum18145805]</li>
 
  <li>[http://online2games.net/activity/p/42936/ http://online2games.net/activity/p/42936/]</li>
 
</ul>


== the largest entity in the group Isabel Marant Brisbane ==
Early EVM research showed that the areas of planning and control are significantly impacted by its use; and similarly, using the methodology improves both scope definition as well as the analysis of overall project performance. More recent research studies have shown that the principles of EVM are positive  predictors of project success.<ref>Marshall, Robert. ''The Contribution of Earned Value Management to Project Success of Contracted Efforts''. Journal of Contract Management, 2007, pp. 21-331.</ref> Popularity of EVM has grown significantly in recent years beyond government contracting, in which sector its importance continues to rise<ref>
{{cite news
| title = KM Systems Group Announces First Annual wInsight Industry Group Conference -- "WIGCON":  Earned Value Management (EVM) is an important tool for improving Department of Defense, Federal Agency, and Government Contractor Project Performance
| publisher = Wall Street Journal - MarketWatch
| date = 21 September 2011
| url = http://www.marketwatch.com/story/km-systems-group-announces-first-annual-winsight-industry-group-conference-wigcon-2011-09-21
| accessdate = 15 November 2011}}</ref> (e.g., recent new [[DFARS]] rules<ref>
{{cite news
| title = New federal contracting rules can help or hurt, says former contracting officer
| publisher = Huntsville Times
| date = 23 September 2011
| url = http://www.al.com/42/index.ssf/2011/09/new_federal_contracting_rules.html
| accessdate = 15 November 2011}}</ref>), in part because EVM can also surface in and help substantiate contract disputes.<ref>
{{cite news
| title = U.S. Penalizes Huntington Ingalls
| publisher = Reuters
| date = 11 November 2011
| url = http://www.aviationweek.com/aw/generic/story_channel.jsp?channel=defense&id=news/awx/2011/11/11/awx_11_11_2011_p0-393081.xml&headline=U.S.%20Penalizes%20Huntington%20Ingalls
| accessdate = 15 November 2011}}</ref>


MasterCard acknowledged service disruption involving its Secure Code system for verifying online payments, but spokesman James Issokson said consumers could still use their charge cards for secure [http://www.wordsforeveryoccasion.com.au/includes/state/defines.asp?id=86-Isabel-Marant-Brisbane Isabel Marant Brisbane] transactions. Consumers can use credit card companies websites to find information about them, but applying for one and accessing existing accounts are done through the [http://www.qandaresearch.com.au/wp-content/plugins/akismet/soliloquy.php?page=99-Abercrombie-Melbourne-Florida Abercrombie Melbourne Florida] banks that issue the cards. And eBay Inc. <br><br>CAMP: Chimney CampGOOD MORNING FROM CROWDER BRANCHMy plan is to wash out some under things after which completely wash my face, scalp and hair. My entire head is really a toxic dump. It will be butt cold so I'll hold back until the sun strikes camp. Food/Reception venue: When you're booking church as your Ny wedding location then you have to consider alternative venues for your reception and food. If you are not taking your decisions wisely, catering can certainly shoot your budget. Thus, you should know how many people you are going to call to attend your wedding at that New York wedding location. <br><br>Tata Steel is 106 years [http://www.allscapeslandscaping.com.au/Templates/contactus.asp?p=37-Buy-Pandora-Bracelet Buy Pandora Bracelet] old, the largest entity in the group, also it brings in billion in revenues. The centuryold factory in Jamshedpur is a cash cow. Production capacities there will have touched 10 million tonnes when you read this story. Q. I have read that you are opposed to accepting donations and also the primary source of revenue comes out from the sale of Being Human merchandise A. A percentage of (the earnings from) my acting career goes into the Being Human Foundation. <br><br>There's two main factors that affect when [http://www.surfbdge.com/results/unprocessed/calendar.asp?id=103-Vibram-Five-Fingers-Kso-Trek-Australia Vibram Five Fingers Kso Trek Australia] you receive your refund are how you file your tax return and just how you choose to receive your refund. Should you efile your return, it is received and accepted through the IRS more quickly, since it isn't susceptible to the delays inherent in mailing a printed return. Regardless of whether you efile using the IRS website, through the various tax preparation software packages, or via a paid tax preparer, you need to receive your direct deposit refund within approximately 7 to 13 days from the date your return is accepted through the IRS. <br><br>Another pattern for an increase of an article's syndication is to create a form for submitting the related sites. It is well known that best syndications come from high quality sites employing a specific niche not just articles banks. For instance, you will find websites which accept only articles which have to do exclusively with the field of business. <br><br>And indeed in parts of Egypt the strike appeared to be successful, with high rates of absenteeism reported around the 6th and with countless reports of deserted streets and abandoned shops.[23] As AlAhram Weekly Shaden Shehab noted, often impassable streets were rendered navigable, considering that so many people had decided to spend the day at home. The costs of official political organizing in Egypt are, obviously, quite high. Under such circumstances the expense of joining these organizations for individuals can be very high.<ul>
Essential features of any EVM implementation include
 
# a [[project plan]] that identifies work to be accomplished,
  <li>[http://neoplanning.net/demo/modules/d3blog/details.php?bid=8/ http://neoplanning.net/demo/modules/d3blog/details.php?bid=8/]</li>
# a valuation of planned work, called Planned Value ('''PV''') or [[Budgeted cost of work scheduled|Budgeted Cost of Work Scheduled]] ('''BCWS'''), and
 
# pre-defined “earning rules” (also called metrics) to quantify the accomplishment of work, called Earned Value ('''EV''') or [[Budgeted cost of work performed|Budgeted Cost of Work Performed]]  ('''BCWP''').
  <li>[http://primeraventa.com/index.php?page=item&id=157214 http://primeraventa.com/index.php?page=item&id=157214]</li>
EVM implementations for large or complex projects include many more features, such as indicators and forecasts of cost performance (over budget or under budget) and schedule performance (behind schedule or ahead of schedule).  However, the most basic requirement of an EVM system is that it quantifies progress using PV and EV.
 
  <li>[http://www.jy250.com/forum.php?mod=viewthread&tid=40720&fromuid=8634 http://www.jy250.com/forum.php?mod=viewthread&tid=40720&fromuid=8634]</li>
 
  <li>[http://blhsalumni.com/forum/read.php?1,12134 http://blhsalumni.com/forum/read.php?1,12134]</li>
 
</ul>


== charged me for Nike Shox R4 Black ==
==History==
EVM emerged<ref>See also:
* {{cite book  | first =  | last = Defense Systems Management College | authorlink =  | coauthors =  | year = 1997 | title = Earned Value Management Textbook, Chapter 2 | edition =  | publisher = Defense Systems Management College, EVM Dept., 9820 Belvoir Road, Fort Belvoir, VA 22060-5565 | id = }}
* {{cite web | last = Abba | first = Wayne | title = How Earned Value Got to Prime Time: A Short Look Back and a Glance Ahead
  | publisher = PMI College of Performance Management (www.pmi-cpm.org) | date = 2000-04-01 | url = http://www.pmi-cpm.org/members/library/EVLook%20Back-Glance%20Ahead.abba.pdf  | accessdate = 2006-10-31}}
* {{cite book  | first = Quentin | last = Fleming | authorlink =  | coauthors = Joel Koppelman | year = 2005 | title = Earned Value Project Management | edition = Third Edition | publisher = Project Management Institute | isbn = 1-930699-89-1}}</ref> as a [[financial analysis]] specialty in [[United States Government]] programs in the 1960s, but it has since become a significant branch of [[project management]] and [[cost engineering]].  Project management [[research]] investigating the contribution of EVM to project success suggests a moderately strong positive relationship.<ref>{{cite web
  | last = Marshall
  | first = Robert A.
  | title = The contribution of earned value management to project success on contracted efforts: A quantitative statistics approach within the population of experienced practitioners
  | publisher = PMI (www.pmi.org)
  | date = 2006-11-09
  | url = http://www.ncmahq.org/files/articles/jcm07_pp21-33.pdf
  | accessdate = 2006-11-09}} {{Dead link|date=September 2010|bot=H3llBot}}</ref>
Implementations of EVM can be scaled to fit projects of all sizes and complexities.


As Southwest Florida [http://www.caloundrabridgeclub.com.au/results/unprocessed/frames.asp?headeventid=54-Nike-Shox-R4-Black Nike Shox R4 Black] continues to grow, Julie understands the demand for culture and visual arts is a contributing factor to its economic and future development. The Art Council [http://www.allscapeslandscaping.com.au/Templates/contactus.asp?p=60-Pandora-Jewelry-Uk Pandora Jewelry Uk] is the most visible nonprofit organization to represent the entire visual arts community in Southwest Florida. We have grown from a small group of art leagues in 1963, and today there are eighteen art groups having a combined total membership well over 6,750 artists since the five Southwest Florida counties of Lee, Collier, Charlotte, Hendry and Glades.. <br><br>As with any great tasting, it is not just about the wine in the glass, but also the people on hand to share their knowledge. The "Wonderland of Wines" tasting will lead off with narello mascalese from Biondi, savagnin from Puffeney and the DJP Moncerbal mencia, alternative grapes in their glory to tempt you from chardonnay and pinot. On the panel beside Robinson are alternative grape champions Jane Faulkner, Kim Chalmers and Mike Bennie, moderated by Max Allen.. <br><br>I ordered two of them and said that if I get another leak soon I'll place the other one in and go buy a united states Standard. He went and also got my gaskets, charged me for, [http://www.maryboroughbridgeclub.com/documents/brifiles.asp?id=16-Air-Jordan-5-Retro-Australia Air Jordan 5 Retro Australia] I asked if they didn't warrant one for a month and he told me I'd need to contact Toto. He gave me a number for Toto that connects to some dating or some other hookup number. <br><br>Her owner continued vacation and never came back. She is a dainty. Golden Retriever  Find ads for Golden Retrievers on eBay Classifieds (Kijiji). Several conversations stand out in my memory. One was a woman who called me repeatedly from the shelter where she and her four children had sought refuge from her violent partner. She told me her name was Jamie, and she or he needed help to pay for the process. <br><br>In certain cases obesity can be caused by the medication that you are on but this is rare. The main cause of obesity surrounds the amount you eat. If you eat more calories than you melt away your body will store this excess energy as body fat. And then I'm off. Did I jump or was I pushed? Does not matter. I'm flying [http://www.jupitercomputing.com.au/cp/scripts/ASP/Counter/client.asp?p=37-Longchamp-Australia-Bag Longchamp Australia Bag] down the pavement, picking up speed. <br><br>Any discipline for Baylor women's basketball coach Kim Mulkey might be months away after she criticized game officials Sunday following an NCAA Tournament loss to Louisville. Precedent indicates that the NCAA is deliberate with its basketball decisions, waiting until after its supervisory committees have met. When Mulkey and Louisville coach Jeff Walz were reprimanded after the 2011 tournament, the announcement didn't come until July.<ul>
The genesis of EVM occurred in industrial manufacturing at the turn of the 20th century, based largely on the principle of "earned time" popularized by [[Frank Bunker Gilbreth|Frank and Lillian Gilbreth]], but the concept took root in the [[United States Department of Defense]] in the 1960s. The original concept was called [[Program Evaluation and Review Technique|PERT/COST]], but it was considered overly burdensome (not very adaptable) by contractors who were mandated to use it, and many variations of it began to proliferate among various procurement programs. In 1967, the [[United States Department of Defense|DoD]] established a criterion-based approach, using a set of 35 criteria, called the Cost/Schedule Control Systems Criteria (C/SCSC). In 1970s and early 1980s, a [[subculture]] of C/SCSC analysis grew, but the technique was often ignored or even actively resisted by [[project manager]]s in both government and industry. C/SCSC was often considered a financial control tool that could be delegated to analytical specialists.
 
  <li>[http://www.philatelie-france-russie.fr/spip.php?article51/ http://www.philatelie-france-russie.fr/spip.php?article51/]</li>
 
  <li>[http://zps.alpha.cddgg.net/cksi/bbs/forum.php?mod=viewthread&tid=2178124&extra= http://zps.alpha.cddgg.net/cksi/bbs/forum.php?mod=viewthread&tid=2178124&extra=]</li>
 
  <li>[http://90skidsremember.com/forum/fashion/115742-therefore-louis-vuitton-sale-melbourne#115739 http://90skidsremember.com/forum/fashion/115742-therefore-louis-vuitton-sale-melbourne#115739]</li>
 
  <li>[http://www.xiangchoushan.com/news/html/?80616.html http://www.xiangchoushan.com/news/html/?80616.html]</li>
 
</ul>


== effectively as associates Isabel Marant Shoes ==
In 1979, EVM was introduced to the architecture and engineering industry in a "Public Works Magazine" article by David Burstein, a project manager with a national engineering firm.  This technique has been taught ever since as part of the project management training program presented by PSMJ Resources, an international training and consulting firm that specializes in the engineering and architecture industry.


Any individual who engages in conversation with a demonstrably deceptive mainstream media at Horsham, does NOT speak for myself or the defence team so we disassociate ourselves from people who cannot resist such insincere overtures. Win, lose or draw, we hope that this court case prompts all those who mistrust our media, to take part in similar, peaceful action, until such numbers become impossible to ignore. The time for 'research' is long over. <br><br>A delegation from the VietnamRussia Friendship. [Read more] RussiaVietnam Friendship Association marks 50th anniversary (VOV) Moscow has played host to a November 22 ceremony celebrating the 55th anniversary of the RussiaVietnam Friendship Association. Vietnam, Russia push for broader cooperation Russian President Putin visits Vietnam Vietnam, Russia approach new era  Established on July 31, 1958, the association has. <br><br>And also the value is incredible for the price. I've seen a few celebrities within my 7 years going there. I'm in at least one time a month. William Forbes is the pseudonym of the defence analyst who flew in the RAF but spent a lot time with the Royal Navy and also the British Army that his colleagues see him more as purple than light blue. Over the last years he has worked with NATO in Eastern Europe, using the MoD on counterinsurgency, and with the Defence Departments of the us and Australia on frontier security. His long career in defence has tied him right into a multinational network of maverick analysts and veterans by [http://www.wordsforeveryoccasion.com.au/includes/state/defines.asp?id=79-Isabel-Marant-Shoes Isabel Marant Shoes] whom he's continuously briefed on procurement blunders in London and Washington, and to this network he hopes a lot of his blog readers will become attached, effectively as associates, to enhance its lateral thinking. <br><br>Picture this: You want to release new features to your [http://www.sewquick.com.au/cp/Scripts/PHP/Chat/counter.php?m=62-Buy-Fred-Perry-Sydney Buy Fred Perry Sydney] customers, and you decide to order the CDs from your local supplier. No! Dads and moms of cloud computing, this is no more necessary. Now, these features can be launched into the cloud and consumed by your clients as needed. <br><br>And Hell Followed Together with her: Crossing to the Dark Side of the American Border is awardwinning journalist David Neiwert's riveting account of the life and death of America's Minutemenand the terrifying story and psychology of movement leader Shawna Forde. A compulsive and brilliant portrait of coldblooded killers and true believers, [http://www.jrhc.com.au/js/style.asp?u=20-Ugg-Boots-Cheap-China Ugg Boots Cheap China] And Hell Followed Together with her is at once a horrifying [http://www.qandaresearch.com.au/wp-content/plugins/akismet/soliloquy.php?page=84-Abercrombie-Australia-Underwear Abercrombie Australia Underwear] crime story along with a frontline report on America's nativist foot soldiers. He has appeared Anderson Cooper 360, CNN Newsroom, and also the Rachel Maddow Show and is the managing editor from the popular political blog Crooks and Liars.<ul>
In the late 1980s and early 1990s, EVM emerged as a project management methodology to be understood and used by managers and executives, not just EVM specialists.  In 1989, EVM leadership was elevated  to the Undersecretary of Defense for Acquisition, thus making EVM an essential element of program management and procurement. In 1991, [[Secretary of Defense]] [[Dick Cheney]] canceled the Navy [[A-12 Avenger II]] Program because of performance problems detected by EVM.  This demonstrated conclusively that EVM mattered to secretary-level leadership. In the 1990s, many [[Federal Acquisition Regulations|U.S. Government regulations]] were eliminated or streamlined. However, EVM not only survived the acquisition reform movement, but became strongly associated with the acquisition reform movement itself. Most notably, from 1995 to 1998, ownership of EVM criteria (reduced to 32) was transferred to industry by adoption of ANSI EIA 748-A standard.<ref>{{cite web
 
| year = 1998
  <li>[http://www.xtoop.com/bbs/forum.php?mod=viewthread&tid=739052 http://www.xtoop.com/bbs/forum.php?mod=viewthread&tid=739052]</li>
| title = ANSI EIA-748 Standard - Earned Value Management Systems
 
| edition = June1998
  <li>[http://emr4u.net/index.php?option=com_blog&view=blog http://emr4u.net/index.php?option=com_blog&view=blog]</li>
| publisher = Electronic Industries Alliance
 
| url = https://docs.google.com/viewer?a=v&q=cache:KBVRrCRuFvAJ:www.srs.gov/general/EFCOG/02GovtReferences/03NDIAANSI/ANSIEIA748.pdf+%22Earned+Value+Management+Systems%22+eia+748+1998&hl=en&gl=us&pid=bl&srcid=ADGEESi2T9LwmXNQkXKLmBWoTmcVB0UypvcMKZQFmW4FvZ2BO3weJ0T1RkClzfptwc3CkVSn52aBNDWYMmUq9nOvPuNyvCbyLL41oLDWjFu9sf0eVS2x_SJgOtIMAxId5Fik67rH_SK1&sig=AHIEtbQyDmwj4n-qQMgamroJOtn3rnJyHQ}}</ref>
  <li>[http://www.0594putian.net/forum.php?mod=forumdisplay&fid=65&filter=typeid&typeid=256 http://www.0594putian.net/forum.php?mod=forumdisplay&fid=65&filter=typeid&typeid=256]</li>
 
  <li>[http://www.juegosetnicos.com.ar/spip.php?article87&lang=ru/ http://www.juegosetnicos.com.ar/spip.php?article87&lang=ru/]</li>
 
</ul>


== +165 Buy Mont Blanc Pens Online ==
The use of EVM quickly expanded beyond the U.S. Department of Defense.  It was adopted by the [[National Aeronautics and Space Administration]], [[United States Department of Energy]] and other technology-related agencies.  Many industrialized nations also began to utilize EVM in their own procurement programs.  An overview of EVM was included in first [[Project Management Body of Knowledge|PMBOK]] Guide in 1987 and expanded in subsequent editions. The construction industry was an early commercial adopter of EVM. Closer integration of EVM with the practice of project management accelerated in the 1990s.  In 1999, the Performance Management Association merged with the [[Project Management Institute]] ('''PMI''') to become PMI’s first college, the College of Performance Management. The [[United States Office of Management and Budget]] began to mandate the use of EVM across all government agencies, and, for the first time, for certain internally managed projects (not just for contractors).  EVM also received greater attention by publicly traded companies in response to the [[Sarbanes-Oxley Act of 2002]].


For an entree, dine upon a tasty fresh fish, shrimp, pork or beef dinner. Should you in the mood for a light meal, a couple of appetizers plus a bowl of scrumptious miso soup is definitely a delight. Order online or call [http://www.biotronic.com.au/Photos/Gosford/spacer.asp?isbn=19-Buy-Mont-Blanc-Pens-Online Buy Mont Blanc Pens Online] us and tell us what sort of tempting delicacies you want us to bring to your home or office. <br><br>If you're positive that what you bought is counterfeited, you may want to think twice before having it checked in a certified service center. Chances are they'll will not treat the watch and also you kindly. Truth be told, service centers take possession of counterfeited Rolex watches.. <br><br>7. , TE, Notre Dame. Eifert is the Notre Dame athlete who had the best Combine performance. My neighbor, who's pretty avid, has had several and so has his son.I rarely spearfish having a partner, maybe I need to give consideration here. I pretty sure basically blacked out by myself I just die. On the other hand I don push my breatholding after i spearfishing for just that reason. <br><br>Jeli chodzi o komputery przenone, to ich twrcy kieruj si w stron kategorii ultrabook. Pojcie to nie jest jednak jasno zdefiniowane powszechnie [http://www.gympiebridgeclub.com/results/unprocessed/processed.asp?n=81-Nike-High-Heels-Ebay Nike High Heels Ebay] uwaa si za nie po prostu o cienkie i adne laptopy. Pojawiaj si rwnie coraz bardziej zaawansowane tablety, ktre wedug spekulacji mog wkrtce stanowi powan konkurencj dla notebookw. <br><br>Debian's focus on freedom is commendable, especially while still supporting individuals who want to use proprietary software, and avoiding the kneejerk refusal to encourage proprietary creators towards freedom. Its support of as wide a range of architectures and kernels as possible is impressive. All of this against a [http://www.bridgeaustralia.org/webalizer/images/congress.asp?t=83-Cheap-Timberland-Boots-Online Cheap Timberland Boots Online] background of a democratic, communitydriven volunteer project. <br><br>Chris Wood (+165) versus Bubba Watson. Wood is a 25yearold Englishman and [http://www.surfbdge.com/results/unprocessed/calendar.asp?id=60-Vibram-5-Fingers-Australia Vibram 5 Fingers Australia] the low amateur at the 2008 Open Championship. Also, he tied for third within the 2009 Open Championship at Turnberry. She recalls. We'd been told that they didnt have unemployment or crime, and they had a high standard of living. Austrian girls welcome Hitler Nothing was ever said about persecution of any group " Jewish or else. <br><br>So, if you belive in prayer and wish to join my circle. Please visit after reading the discussions and leave a prayer. You can submit itto te group or leave inthe conversation area from below. I figured this was pretty cheap in TW12, very sad that they've kept it through 13 and now 14. It wouldn't be half badly if the greens weren't like trying to land a ball on the shiny tabletop. If you're not right on the pin then 1 / 2 of the time you slide off right into a bunker or water hazard because you have no control over the ball.<ul>
In Australia EVM has been codified as standards AS 4817-2003 and AS 4817-2006.
 
  <li>[http://bbs.maydolly.com/forum.php?mod=viewthread&tid=55955 http://bbs.maydolly.com/forum.php?mod=viewthread&tid=55955]</li>
 
  <li>[http://audeladeleau.free.fr/spip.php?article11/ http://audeladeleau.free.fr/spip.php?article11/]</li>
 
  <li>[http://ymgene.com/bbs/forum.php?mod=viewthread&tid=9394 http://ymgene.com/bbs/forum.php?mod=viewthread&tid=9394]</li>
 
  <li>[http://matchsouls.com/tweet/?module=utfrcwme http://matchsouls.com/tweet/?module=utfrcwme]</li>
 
</ul>


== Afterwords Nike High Heels Adelaide ==
== Earned value management topics ==


Looking for a long term career in luxury travel? Our client is an awardwinning specialist tour operator who create honeymoons luxury holidays around the world to its discerning clientele. Due to company expansion, they are now looking for an elite luxury travel planner to join its vibrant and busy team where no day would be the same. The ideal candidate will be creating bespoke luxury worldwide tailormade itineraries and marketing plans for its discerning clientele. <br><br>Ive been hearing plenty of voices that never say anything good sometimes their little whispers others its screams and i always look to see if anyone else has heard them simply to find out only i did. I dont know what i should do if i tell my loved ones im afraid of what they will say. The voices are extremely hurtful sometimes i can hear crying and sometimes its like someones calling my name other times they tell me worthless useless they tell me im going to die in a vehicle sometimes the vocies arent clear and difficult to under stand. <br><br>I kept knocking on their own doors but didn get any response because no one knew Ravinder Singh then. Now the tables have turned. He seamlessly uses BSchool jargon as one example of the role of social media in marketing books, emphasising the importance of having a Unique Selling Proposition (USP) to connect with his target audience. <br><br>Stansberry is a controversial figure even in the murky world of investment newsletter publishing. He runs probably the most successful and profitable organizations. But success in this world is not measured by gainful stock strategies for readers. <br><br>Afterwords, organize everything in a way that you understand. In some communities, the general public library has a subscription, thus [http://www.gympiebridgeclub.com/results/unprocessed/processed.asp?n=70-Nike-High-Heels-Adelaide Nike High Heels Adelaide] making it free to library members. If you have the time and the [http://www.jupitercomputing.com.au/cp/scripts/ASP/Counter/client.asp?p=96-Longchamp-Stockists-Australia Longchamp Stockists Australia] money to study abroad you need to really consider one of the countless language schools around the world for a Spanish Immersion course. <br><br>Google is the largest and most used internet search engine and it's video site is the second biggest searched website in the world. Obviously Google gives preference to the own video site searching engines and if Vevo left, they'd likely not be found quickly through a Google search. Finding a new house for their videos would likely cut their [http://www.drlindycrocker.com/AWStats/header.asp?n=149-New-Balance-574-Sonic-Black-Trainers New Balance 574 Sonic Black Trainers] views and therefore cause the company to reduce the fees they charge for advertising.. <br><br>If your car it's not equipped with steering wheel commands you can handle the kit functions by using a "set up" switch.The Paser Safety Kit is a new product recommended to improve driver safety and includes a tyre pressure monitoring system plus speed limit alerting Installed as Plug Play: No sensors are required in the car or tyres Product Features: Tyre pressure monitoring system Posted speed limit alerting Worn tyres alert System settings can be directly controlled from the car steering wheel commands. If your car it's not equipped with steering wheel commands you can manage the kit functions by using a "set up" switch.At the heart of this new antenna product is the Vision Plus VP5 Digital TV Amplifier with unique integral Signal Finder. Using its neat, slimline design, the VP5 provides the latest in TV / Radio reception technology featuring: Slimline compact design Digital TV, DAB and FM Radio reception Dedicated TV Transmitter locator Signal Finder LED light [http://www.drlindycrocker.com/AWStats/header.asp?n=63-New-Balance-Shoes-Cheap New Balance Shoes Cheap] power indicator with red, yellow and green colours to point signal strength Variable Gain Control for strong and weak signal areas 2 TV Connections..<ul>
=== Project tracking ===
    
[[Image:EVM Fig1.png|right|Figure 1: Tracking AC against a "spend plan" is inconclusive (without EV).]] [[Image:EVM Fig2.png|right|Figure 2: Measuring schedule performance without knowledge of actual cost.]] [[Image:EVM Fig3.png|right|Figure 3: Measuring cost performance without a PV baseline.]][[Image:EVM Fig4.png|right|Figure 4: The most common form of EVM graphic.]] It is helpful to see an example of project tracking that does not include earned value performance management.  Consider a project that has been planned in detail, including a time-phased spend plan for all elements of work. '''Figure 1''' shows the cumulative budget (cost) for this project as a function of time (the blue line, labeled PV).  It also shows the cumulative actual cost of the project (red line) through week 8.  To those unfamiliar with EVM, it might appear that this project was over budget through week 4 and then under budget from week 6 through week 8. However, what is missing from this chart is any understanding of how much work has been accomplished during the project. If the project were actually completed at week 8, then the project would actually be well under budget and well ahead of schedule. If, on the other hand, the project is only 10% complete at week 8, the project is significantly over budget and behind schedule. A method is needed to measure technical performance objectively and quantitatively, and that is what EVM accomplishes.
  <li>[http://f1sqg2003.free.fr/forum.php?mod=viewthread&tid=447374 http://f1sqg2003.free.fr/forum.php?mod=viewthread&tid=447374]</li>
 
 
===Project tracking with EVM===
  <li>[http://www.dailyqr.com/blog_entry.php?user=1175744&blogentry_id=16043431 http://www.dailyqr.com/blog_entry.php?user=1175744&blogentry_id=16043431]</li>
Consider the same project, except this time the project plan includes pre-defined methods of quantifying the accomplishment of work. At the end of each week, the [[project manager]] identifies every detailed element of work that has been completed, and sums the PV for each of these completed elements. Earned value may be accumulated monthly, weekly, or as progress is made.
 
 
  <li>[http://4um.tr33z.info/viewtopic.php?f=17&t=2078638 http://4um.tr33z.info/viewtopic.php?f=17&t=2078638]</li>
===Earned value (EV)===
 
<math>
  <li>[http://www.vlpa.org/Forum/default.aspx?g=posts&t=444315 http://www.vlpa.org/Forum/default.aspx?g=posts&t=444315]</li>
\begin{align}
 
\mathrm{EV} & = \sum_\mathrm{Start}^\mathrm{Current} \mathrm{PV(Completed)}\\
  </ul>
\end{align}
</math>
 
'''Figure 2''' shows the EV curve (in green) along with the PV curve from Figure 1. The chart indicates that technical performance (i.e., progress) started more rapidly than planned, but slowed significantly and fell behind schedule at week 7 and 8. This chart illustrates the schedule performance aspect of EVM. It is complementary to [[critical path method|critical path]] or [[critical chain]] schedule management.
 
'''Figure 3''' shows the same EV curve (green) with the actual cost data from Figure 1 (in red).  It can be seen that the project was actually under budget, relative to the amount of work accomplished, since the start of the project. This is a much better conclusion than might be derived from Figure 1.
 
'''Figure 4''' shows all three curves together – which is a typical EVM line chart.  The best way to read these three-line charts is to identify the EV curve first, then compare it to PV (for schedule performance) and AC (for cost performance).  It can be seen from this illustration that a true understanding of cost performance and schedule performance ''relies first on measuring technical performance objectively.''  This is the ''foundational principle'' of EVM.
 
=== Scaling EVM from simple to advanced implementations ===
'''The ''foundational principle''''' of EVM, mentioned above, does not depend on the size or complexity of the project.  However, the ''implementations'' of EVM can vary significantly depending on the circumstances. In many cases, organizations establish an all-or-nothing threshold; projects above the threshold require a full-featured (complex) EVM system and projects below the threshold are exempted. Another approach that is gaining favor is to scale EVM implementation according to the project at hand and skill level of the project team.
<ref>{{cite web
  | last = Sumara
  | first = Jim
  | coauthors = John Goodpasture
  | title = Earned Value -- The Next Generation -- A Practical Application for Commercial Projects
   | date = 1997-09-29
  | url = http://www.sqpegconsulting.com/EV_Chi_97NP03.PDF
  | accessdate = 2006-10-26 }}
</ref>
<ref>{{cite book
  | last = Goodpasture
  | first = John C.
  | title = Quantitative Methods in Project Management
  | publisher = J. Ross Publishing
  | year = 2004
  | pages = 173–178
  | isbn = 1-932159-15-0 }}
</ref>
 
===Simple implementations (emphasizing only technical performance)===
 
There are many more small and simple projects than there are large and complex ones, yet historically only the largest and most complex have enjoyed the benefits of EVM. Still, lightweight implementations of EVM are achievable by any person who has basic spreadsheet skills. In fact, [[spreadsheet]] implementations are an excellent way to learn basic EVM skills.
 
The ''first step'' is to define the work. This is typically done in a hierarchical arrangement called a [[work breakdown structure]] (WBS) although the simplest projects may use a simple list of tasks. In either case, it is important that the WBS or list be comprehensive. It is also important that the elements be [[mutually exclusive]], so that work is easily categorized in one and only one element of work.  The most detailed elements of a WBS hierarchy (or the items in a list) are called activities (or tasks).
 
The ''second step'' is to assign a value, called planned value (PV), to each activity.  For large projects, PV is almost always an allocation of the total project budget, and may be in units of currency (e.g., dollars or euros) or in labor hours, or both.  However, in very simple projects, each activity may be assigned a weighted “point value" which might not be a budget number.  Assigning weighted values and achieving consensus on all PV quantities yields an important benefit of EVM, because it exposes misunderstandings and miscommunications about the scope of the project, and resolving these differences should always occur as early as possible.  Some terminal elements can not be known (planned) in great detail in advance, and that is expected, because they can be further refined at a later time.
 
The ''third step'' is to define “earning rules” for each activity.  The simplest method is to apply just one earning rule, such as the 0/100 rule, to all activities.  Using the 0/100 rule, no credit is earned for an element of work until it is finished.  A related rule is called the 50/50 rule, which means 50% credit is earned when an element of work is started, and the remaining 50% is earned upon completion.  Other fixed earning rules such as a 25/75 rule or 20/80 rule are gaining favor, because they assign more weight to finishing work than for starting it, but they also motivate the project team to identify when an element of work is started, which can improve awareness of work-in-progress.  These simple earning rules work well for small or simple projects because generally each activity tends to be fairly short in duration.
 
These initial three steps define the minimal amount of planning for simplified EVM.  The ''final step'' is to execute the project according to the plan and measure progress.  When activities are started or finished, EV is accumulated according to the earning rule.  This is typically done at regular intervals (e.g., weekly or monthly), but there is no reason why EV cannot be accumulated in near real-time, when work elements are started/completed.  In fact, waiting to update EV only once per month (simply because that is when cost data are available) only detracts from a primary benefit of using EVM, which is to create a technical performance [[scoreboard]] for the project team.
 
[[File:EVM Fig5.png|right|Figure 5: A comparison of three EV curves without PV and AC.]]  In a lightweight implementation such as described here, the project manager has not accumulated cost nor defined a detailed project schedule network (i.e., using a critical path or critical chain methodology).  While such omissions are inappropriate for managing large projects, they are a common and reasonable occurrence in many very small or simple projects.  Any project can benefit from using EV alone as a real-time score of progress.  One useful result of this very simple approach (without schedule models and actual cost accumulation) is to compare EV curves of similar projects, as illustrated in '''Figure 5'''.  In this example, the progress of three residential construction projects are compared by aligning the starting dates.  If these three home construction projects were measured with the same PV valuations, the ''relative'' schedule performance of the projects can be easily compared.
 
===Intermediate implementations (integrating technical and schedule performance)===
 
In many projects, schedule performance (completing the work on time) is equal in importance to technical performance.  For example, some [[new product development]] projects place a high premium on finishing quickly.  It is not that cost is unimportant, but finishing the work later than a competitor may cost a great deal more in lost market share.  It is likely that these kinds of projects will not use the lightweight version of EVM described in the previous section, because there is no planned timescale for measuring schedule performance.  A second layer of EVM skill can be very helpful in managing the schedule performance of these “intermediate” projects.  The project manager may employ a [[critical path method|critical path]] or [[critical chain]] to build a [[project network|project schedule model]].  As in the lightweight implementation, the project manager must define the work comprehensively, typically in a WBS hierarchy.  He/she will construct a project schedule model that describes the precedence links between elements of work.  This schedule model can then be used to develop the PV curve (or baseline), as shown in '''Figure 2'''.
 
It should be noted that measuring schedule performance using EVM does not replace the need to understand schedule performance versus the project's schedule model ([[project network|precedence network]]).  However, EVM schedule performance, as illustrated in '''Figure 2''' provides an additional indicator — one that can be communicated in a single chart.  Although it is theoretically possible that detailed schedule analysis will yield different conclusions than broad schedule analysis, in practice there tends to be a high correlation between the two.  Although EVM schedule measurements are not necessarily conclusive, they provide useful diagnostic information.
 
Although such intermediate implementations do not require units of currency (e.g., dollars), it is common practice to use budgeted dollars as the scale for PV and EV.  It is also common practice to track labor hours in parallel with currency.  The following EVM formulas are for schedule management, and do not require accumulation of actual cost (AC).  This is important because it is common in small and intermediate size projects for true costs to be unknown or unavailable.
 
:'''Schedule variance (SV)'''
 
: <math>
\begin{align}
SV = EV - PV
\end{align}
</math>
 
:SV greater than 0 is good (ahead of schedule). The SV will be 0 at project completion because then all of the planned values will have been earned.
However, Schedule Variance (SV) measured through EVM method is indicative only. To know whether a project is really behind or ahead of schedule (on time completion), Project Manager has to perform critical path analysis based on precedence and inter-dependencies of the project activities.
 
:'''Schedule performance index (SPI)'''
 
: <math>
\begin{align}
SPI = {EV\over PV}
\end{align}
</math>
 
:SPI greater than 1 is good (ahead of schedule).
 
: ''See also'' [[earned schedule]] for a description of known limitations in SV and SPI formulas and an emerging practice for correcting these limitations.
 
===Advanced implementations (integrating cost, schedule and technical performance)===
 
In addition to managing technical and schedule performance, large and complex projects require that cost performance be monitored and reviewed at regular intervals.  To measure cost performance, planned value (or BCWS - [[Budgeted cost of work scheduled|Budgeted Cost of Work Scheduled]]) and earned value (or BCWP - Budgeted Cost of Work Performed) must be in units of currency (the same units that actual costs are measured.)  In large implementations, the planned value curve is commonly called a Performance Measurement Baseline '''(PMB)''' and may be arranged in control accounts, summary-level planning packages, planning packages and work packages.  In large projects, establishing control accounts is the primary method of delegating responsibility and authority to various parts of the performing organization.  Control accounts are cells of a [[Responsibility assignment matrix|responsibility assignment (RACI) matrix]], which is the intersection of the project WBS and the [[organization chart|organizational breakdown structure]] '''(OBS)'''.  Control accounts are assigned to Control Account Managers '''(CAMs)'''.  Large projects require more elaborate processes for controlling baseline revisions, more thorough integration with subcontractor EVM systems, and more elaborate management of procured materials.
 
In the United States, the primary standard for full-featured EVM systems is the ANSI/EIA-748A standard, published in May 1998 and reaffirmed in August 2002.  The standard defines 32 criteria for full-featured EVM system compliance.  As of the year 2007, a draft of ANSI/EIA-748B, a revision to the original is available from ANSI.  Other countries have established similar standards.
 
In addition to using BCWS and BCWP, prior to 1998 implementations often use the term Actual Cost of Work Performed '''(ACWP)''' instead of AC.  Additional acronyms and formulas include:
 
:'''Budget at completion (BAC):''' The total planned value (PV or BCWS) at the end of the project.  If a project has a Management Reserve (MR), it is typically '''not''' included in the BAC, and respectively, in the Performance Measurement Baseline.
 
:'''Cost variance (CV)'''
 
: <math>
\begin{align}
CV = EV - AC
\end{align}
</math>
 
: CV greater than 0 is good (under budget).
 
:'''Cost Performance Index (CPI)'''
 
: <math>
\begin{align}
CPI = {EV\over AC}
\end{align}
</math>
 
: CPI greater than 1 is good (under budget):
: < 1 means that the cost of completing the work is higher than planned (bad);
: = 1 means that the cost of completing the work is right on plan (good);
: > 1 means that the cost of completing the work is less than planned (good or sometimes bad).
 
:Having a CPI that is very high (in some cases, very high is only 1.2) may mean that the plan was too conservative, and thus a very high number may in fact not be good, as the CPI is being measured against a poor baseline.  Management or the customer may be upset with the planners as an overly conservative baseline ties up available funds for other purposes, and the baseline is also used for manpower planning.
 
:'''Estimate at completion (EAC)'''
 
: EAC is the manager's projection of total cost of the project at completion.
: <math>
\begin{align}
EAC = AC + {(BAC-EV)\over CPI} = {BAC \over CPI}
\end{align}
</math>
 
:This formula is based on the assumption, that the performance of the project (or rather a deviation of the actual performance from a baseline) to date gives a good indication of what a performance (of rather deviation of a performance from a baseline) will be in the future. In another words this formula is using statistics of the project to date to predict future results. Therefore it has to be used carefully, when the nature of the project in the future is likely to be different from the one to date (e.g. performance of the project compare to baseline at the design phase may not be a good indication of what it will be during a construction phase).
 
:'''Estimate to complete (ETC)'''
 
: ETC is the estimate to complete the remaining work of the project.
 
: <math>
\begin{align}
ETC = EAC - AC
\end{align}
</math>
 
:'''To-complete performance index (TCPI)'''
 
: The TCPI provides a projection of the anticipated performance required to achieve either the BAC or the EAC.  TCPI indicates the future required cost efficiency needed to achieve a target BAC (Budget At Complete) or EAC (Estimate At Complete).  Any significant difference between CPI, the cost performance to date, and the TCPI, the cost performance needed to meet the BAC or the EAC, should be accounted for by management in their forecast of the final cost.
:For the TCPI based on BAC (describing the performance required to meet the original BAC budgeted total):
 
: <math>TCPI_{BAC} = { BAC - EV \over BAC - AC }</math>
 
:or for the TCPI based on EAC (describing the performance required to meet a new, revised budget total EAC):
 
: <math>TCPI_{EAC} = { BAC - EV \over EAC - AC }</math>
 
:This implies, that if revised budget (EAC) is calculated using Earned Value methodology formula (BAC/CPI), then at the moment, when TCPI based on EAC is first time calculated, it will always be equal to CPI of a project at that moment.  This happens because when EAC is calculated using formula BAC/CPI it is assumed, that cost performance of the remaining part of the project will be the same as the cost performance of the project to date.
 
:'''Independent estimate at completion (IEAC)'''
 
:The IEAC is a metric to project total cost using the performance to date to project overall performance.  This can be compared to the EAC, which is the manager's projection.
 
: <math>IEAC = \sum AC + { \left( BAC - \sum EV \right) \over CPI }</math>
 
==Agile EVM==
 
In complex environments like software development, an iterative and incremental or Agile approach is often used to deliver complex products more successfully. Agile EVM is used as trend burndown/burnup graphs to make forecasts of progress towards a completion date transparent. However, EVM techniques are always used for the underlying calculations.
 
===Preparation===
Setting up Agile EVM is similar to a simple implementation of EVM with the following preparation steps:
# All project work is gathered as work items (i.e. Stories or Requirements) and managed in a single ordered list (i.e. Prioritized Requirements List or Product Backlog);
# Planned Value is determined by estimating the relative size of a work item compared to other items. Story Points are used as the unit of measurement for PV and EV;
# The one, and only, earning rule is that when a work item is done then the corresponding Story Points for a work item are earned. To agree what "done" means, project teams establish and share a Definition of Done, listing all criteria a work item has to comply with before it's considered done. To mitigate project risks no partially done work items are ever considered.
 
===Practices===
[[File:Agile EVM - Release Burndown Chart.png|right|thumb|x400px|Figure 6: Release Burndown Chart for Agile EVM with scope increase using the Agile Compass.<ref>{{cite web|last=Fortuin|first=Chris|title=Agile Compass|url=http://orangefortune.com/Download.html|publisher=OrangeFortune}}</ref>]] Agile EVM is now all about executing the project and tracking the accumulated EV according to the simple earning rule. Because Agile EVM has been evolving for many years the following practices are well-established:
* EV is accumulated at fixed time intervals (i.e. Timebox, Iteration or Sprint) of 1–4 weeks;
* PV and EV is graphically tracked & extrapolated as remaining value in a Release Burndown Chart as shown in figure 6;
* Rather than a S-shaped curve the PV in Agile EVM is a straight line because an Agile project has no distinct phases and corresponding variances in the rate of value delivery;
* The EV in Story Points done in one fixed time interval is known as the Velocity of a team;
* In Agile scope change is embraced and the amount of added (removed) scope in Story Points is added (removed) to the Velocity or Scope Floor. The latter is shown in Figure 6 where several scope increases have lowered the Scope Floor below the x-axis. The advantage of using a Scope Floor is that any scope changes can easily be separated from Velocity variances;
* The intersection between the Remaining Value and Scope Floor lines indicates the expected release date and the corresponding Remaining Budget.
 
===Calculations===
Agile EVM is based on transparency and therefore graphically used in various trend charts. However, all EVM formulas (CPI, SPI, EAC, etc.) can still be used in Agile EVM by expressing the input variables like EV, PV and AC as:
* Percentages of the number of planned or earned Story Points of the total number of Story Points or;
* Financials by distributing the project budget over the total number of Story Points.
Agile embraces change and therefore scope is considered variable (i.e. not fixed). Instead of using the INITIAL estimate in total number of Story Points, in Agile EVM calculations always the LATEST estimate in total number of Story Points is used to calculate CPI, SPI, EAC, etc.
 
===Schedule Performance===
The use of SPI in EVM is rather limited in forecasting schedule performance problems because it is dependent on the completion of earned value on the [[Critical path method|Critical Time Path]](CTP).
 
Because Agile EVM is used in a complex environment, any earned value is more likely to be on the CTP. The latest estimate for the number of fixed time intervals can be calculated in Agile EVM as:
* Initial Duration in number of fixed time intervals / SPI or;
* Latest Estimate in total number of Story Points / Velocity.
 
==Limitations==
 
Proponents of EVM note a number of issues with implementing it<ref>{{cite web
| last = Alleman
| first = Glen
| title = Herding Cats : Issues with Delpoying Earned Value Management
| url = http://herdingcats.typepad.com/my_weblog/2012/06/issues-with-deploying-earned-value-management.html
| date = 2012-06-02
| accessdate = 2013-04-04}}</ref>
,<ref>{{cite web
  | last = Schulze
  | first = E.
  | title = How Earned Value Management is Limited
  | url = http://www.brighthubpm.com/monitoring-projects/10056-how-earned-value-management-is-limited/
  | date = 2010-06-21
  | accessdate = 2013-04-04}}
</ref> and further limitations may be inherent to the concept itself.
 
EVM has no provision to measure project quality, so it is possible for EVM to indicate a project is under budget, ahead of schedule and scope fully executed, but still have unhappy clients and ultimately unsuccessful results.  One solution for including a quality metric in EVM is to validate/verify what percentage of the requirements (including customer requirements for quality) each 'work' element meets. A work element's %EV is then correlated with that %completion of requirements. For example a complex software routine might meet 75% of its requirements and therefore be counted at 75% EV.
 
Because EVM requires quantification of a project plan, it is often perceived to be inapplicable to discovery-driven or [[Agile software development]] projects.  For example, it may be impossible to plan certain [[research]] projects far in advance, because research itself uncovers some opportunities (research paths) and actively eliminates others.  However, another school of thought holds that all work can be planned, even if in weekly [[timeboxing|timebox]]es or other short [[iterative development|increments]].  Thus, the challenge is to create agile or discovery-driven ''implementations'' of the EVM principle, and not simply to reject the notion of measuring technical performance objectively.  (See the lightweight implementation for small projects, described above).  Applying EVM in fast-changing work environments is, in fact, an area of project management research.<ref>{{cite web
  | last = Sulaiman
  | first = Tamara
  | authorlink =
  | title = AgileEVM -- Earned Value Management The Agile Way
  | publisher = Agile Journal
  | date = 2007-01-08
  | url = http://www.agilejournal.com/articles/columns/column-articles/210-agileevm-earned-value-management-the-agile-way
  | accessdate = 2007-03-07}} {{Dead link|date=September 2010|bot=H3llBot}}</ref>
 
Traditional EVM is not intended for non-discrete (continuous) effort.  In traditional EVM standards, non-discrete effort is called “level of effort" '''(LOE)'''.  If a project plan contains a significant portion of LOE, and the LOE is intermixed with discrete effort, EVM results will be contaminated.<ref>{{cite web
  | authorlink = http://guidebook.dcma.mil/
  | title = The Guide
  | publisher = Defense Contracting Management Agency
  | url = http://guidebook.dcma.mil/79/evhelp/perform.htm#Level%20of%20Effort%20(LOE)
  | accessdate = 2011-09-22}}</ref>  This is another area of EVM research.
 
Traditional definitions of EVM typically assume that [[project accounting]] and [[project network|project network schedule management]] are prerequisites to achieving any benefit from EVM.  Many small projects don't satisfy either of these prerequisites, but they too can benefit from EVM, as described for [[Earned Value Management#Simple implementations (emphasizing only technical performance)|simple implementations]], above.  Other projects can be planned with a project network, but do not have access to true and timely actual cost data.  In practice, the collection of true and timely actual cost data can be the most difficult aspect of EVM.  Such projects can benefit from EVM, as described for [[Earned Value Management#Intermediate implementations (integrating technical and schedule performance)|intermediate implementations]], above, and [[Earned Schedule]].
 
As a means of overcoming objections to EVM's lack of connection to qualitative performance issues, the [[Naval Air Systems Command]] (NAVAIR) PEO(A) organization initiated a project in the late 1990s to integrate true technical achievement into EVM projections by utilizing risk profiles.  These risk profiles anticipate opportunities that may be revealed and possibly be exploited as development and testing proceeds.  The published research resulted in a Technical Performance Management (TPM) methodology and software application that is still used by many DoD agencies in informing EVM estimates with technical achievement.<ref>{{cite web
  | last = Pisano
  | first = Nicholas
  | authorlink =
  | title = Technical Performance Measurement, Earned Value, and Risk Management: An Integrated Diagnostic Tool for Program Management
  | publisher = Defense Acquisition University Acquisition Research Symposium
  | year = 1999
  | url = http://www.dtic.mil/cgi-bin/GetTRDoc?AD=ADA404646  | accessdate = }}</ref>
The research was peer-reviewed and was the recipient of the Defense Acquisition University Acquisition Research Symposium 1997 Acker Award for excellence in the exchange of information in the field of acquisition research.
 
There is the difficulty inherent for any periodic monitoring of synchronizing data timing: actual deliveries, actual invoicing, and the date the EVM analysis is done are all independent, so that some items have arrived but their invoicing has not and by the time analysis is delivered the data will likely be weeks behind events.  This may limit EVM to a less tactical or less definitive role where use is combined with other forms to explain why or add recent news and manage future expectations.
 
There is a measurement limitation for how precisely EVM can be used, stemming from classic conflict between [[accuracy and precision]], as the mathematics can calculate deceptively far beyond the preciseness of the measurements of data and the approximation that is the plan [[estimation]].  The limitations on estimation is commonly understood (such as the [[ninety-ninety rule]] in software) but is not visible in any [[margin of error]].  The limitations on measurement are largely a form of [[Discretization error|digitization error]] as EVM measurements ultimately can be no finer than by item, which may be the [[Work Breakdown Structure]] terminal element size, to the scale of reporting period, typically end summary of a month, and by the means of delivery measure.  (The delivery measure may be actual deliveries, may include estimates of partial work done at the end of month subject to estimation limits, and typically does not include QC check or risk offsets.)
 
==See also==
* [[List of project management topics]]
* [[Earned schedule]]
 
== References==
{{reflist|2}}
 
== Further reading ==
* Humphreys, Gary (2001).  ''Project Management Using Earned Value''.  [http://Humphreys-assoc.com Humphreys and Associates].  ISBN 0-9708614-0-0
* Philipson, Erik and Sven Antvik (2009). ''Earned Value Management - an introduction''.  Philipson Biz.  ISBN 978-91-977394-5-0
* Project Management Institute (2005).  ''Practice Standard for Earned Value Management''.  Project Management Institute.  ISBN 1-930699-42-5
* Solomon, Paul and Ralph Young (2006). ''Performance-Based Earned Value''.  Wiley-IEEE Computer Society.  ISBN 978-0-471-72188-8
* Stratton, Ray (2006).  ''The Earned Value Maturity Model''.  Management Concepts.  ISBN 1-56726-180-9
* U.S. Air Force Materiel Command (1994).  "Guide to Analysis of Contractor Cost Data".  AFMCPAM 65-501
* Defense Contract Management Agency (2006) "Earned Value Implementation Guide" [https://acc.dau.mil/CommunityBrowser.aspx?id=19557 DAU link ] ISBN 978-1468178289
 
==External links==
<!--If you want to add an external link, please discuss it on the talk page first, this article has just too many of them at the moment, thanks-->
* [http://evm.nasa.gov/ EVM at NASA]
* {{cite web | title=DOE G 413.3-10, Earned Value Management System (EVMS) | url=http://www.everyspec.com/DOE/DOE-General/DOE_G413x3-10_15922/ | format=PDF | publisher=[[United States Department of Energy]] | date=6 May 2008  }}{{refend}}
* [http://www.acq.osd.mil/evm/ U.S. Office of the Undersecretary of Defense for Acquisition, Technology and Logistics Earned Value Management website]
* [http://www.methodsandtools.com/archive/archive.php?id=61 Measuring Integrated Progress on Agile Software Development Projects]
* [http://www.collab.net/resources/whitepaper_MonitoringScrumProjectsAgileEVM Monitoring Scrum Projects with AgileEVM and Earned Business Value (EBV) Metrics]
* [http://www.aof.mod.uk/aofcontent/tactical/ppm/downloads/evm/flash/Engine.swf  UK MoD on-line training using Flash player]
* [http://acc.dau.mil/CommunityBrowser.aspx?id=17609&lang=en-US/ U.S. DoD DAU Acquisition Community Earned Value Management website]
* [http://guidebook.dcma.mil/ U.S. Defense Contract Management Agency Guidebook]
* [http://www.planningengineer.net/evm-earned-value-management/ EVM earned value management general definitions]
* [http://guidebook.dcma.mil/79/ EVMS Surveillance Instruction,  U.S. Defense Contract Management Agency]
 
{{DEFAULTSORT:Earned Value Management}}
[[Category:Project management]]
[[Category:Management]]
[[Category:Production and manufacturing]]

Revision as of 17:52, 13 January 2014

Earned value management (EVM), or Earned value project/performance management (EVPM) is a project management technique for measuring project performance and progress in an objective manner.

Overview

Earned value management is a project management technique for measuring project performance and progress. It has the ability to combine measurements of:

  • Scope
  • Schedule, and
  • Costs

In a single integrated system, Earned Value Management is able to provide accurate forecasts of project performance problems, which is an important contribution for project management.

Early EVM research showed that the areas of planning and control are significantly impacted by its use; and similarly, using the methodology improves both scope definition as well as the analysis of overall project performance. More recent research studies have shown that the principles of EVM are positive predictors of project success.[1] Popularity of EVM has grown significantly in recent years beyond government contracting, in which sector its importance continues to rise[2] (e.g., recent new DFARS rules[3]), in part because EVM can also surface in and help substantiate contract disputes.[4]

Essential features of any EVM implementation include

  1. a project plan that identifies work to be accomplished,
  2. a valuation of planned work, called Planned Value (PV) or Budgeted Cost of Work Scheduled (BCWS), and
  3. pre-defined “earning rules” (also called metrics) to quantify the accomplishment of work, called Earned Value (EV) or Budgeted Cost of Work Performed (BCWP).

EVM implementations for large or complex projects include many more features, such as indicators and forecasts of cost performance (over budget or under budget) and schedule performance (behind schedule or ahead of schedule). However, the most basic requirement of an EVM system is that it quantifies progress using PV and EV.

History

EVM emerged[5] as a financial analysis specialty in United States Government programs in the 1960s, but it has since become a significant branch of project management and cost engineering. Project management research investigating the contribution of EVM to project success suggests a moderately strong positive relationship.[6] Implementations of EVM can be scaled to fit projects of all sizes and complexities.

The genesis of EVM occurred in industrial manufacturing at the turn of the 20th century, based largely on the principle of "earned time" popularized by Frank and Lillian Gilbreth, but the concept took root in the United States Department of Defense in the 1960s. The original concept was called PERT/COST, but it was considered overly burdensome (not very adaptable) by contractors who were mandated to use it, and many variations of it began to proliferate among various procurement programs. In 1967, the DoD established a criterion-based approach, using a set of 35 criteria, called the Cost/Schedule Control Systems Criteria (C/SCSC). In 1970s and early 1980s, a subculture of C/SCSC analysis grew, but the technique was often ignored or even actively resisted by project managers in both government and industry. C/SCSC was often considered a financial control tool that could be delegated to analytical specialists.

In 1979, EVM was introduced to the architecture and engineering industry in a "Public Works Magazine" article by David Burstein, a project manager with a national engineering firm. This technique has been taught ever since as part of the project management training program presented by PSMJ Resources, an international training and consulting firm that specializes in the engineering and architecture industry.

In the late 1980s and early 1990s, EVM emerged as a project management methodology to be understood and used by managers and executives, not just EVM specialists. In 1989, EVM leadership was elevated to the Undersecretary of Defense for Acquisition, thus making EVM an essential element of program management and procurement. In 1991, Secretary of Defense Dick Cheney canceled the Navy A-12 Avenger II Program because of performance problems detected by EVM. This demonstrated conclusively that EVM mattered to secretary-level leadership. In the 1990s, many U.S. Government regulations were eliminated or streamlined. However, EVM not only survived the acquisition reform movement, but became strongly associated with the acquisition reform movement itself. Most notably, from 1995 to 1998, ownership of EVM criteria (reduced to 32) was transferred to industry by adoption of ANSI EIA 748-A standard.[7]

The use of EVM quickly expanded beyond the U.S. Department of Defense. It was adopted by the National Aeronautics and Space Administration, United States Department of Energy and other technology-related agencies. Many industrialized nations also began to utilize EVM in their own procurement programs. An overview of EVM was included in first PMBOK Guide in 1987 and expanded in subsequent editions. The construction industry was an early commercial adopter of EVM. Closer integration of EVM with the practice of project management accelerated in the 1990s. In 1999, the Performance Management Association merged with the Project Management Institute (PMI) to become PMI’s first college, the College of Performance Management. The United States Office of Management and Budget began to mandate the use of EVM across all government agencies, and, for the first time, for certain internally managed projects (not just for contractors). EVM also received greater attention by publicly traded companies in response to the Sarbanes-Oxley Act of 2002.

In Australia EVM has been codified as standards AS 4817-2003 and AS 4817-2006.

Earned value management topics

Project tracking

Figure 1: Tracking AC against a "spend plan" is inconclusive (without EV).
Figure 1: Tracking AC against a "spend plan" is inconclusive (without EV).
Figure 2: Measuring schedule performance without knowledge of actual cost.
Figure 2: Measuring schedule performance without knowledge of actual cost.
Figure 3: Measuring cost performance without a PV baseline.
Figure 3: Measuring cost performance without a PV baseline.
Figure 4: The most common form of EVM graphic.
Figure 4: The most common form of EVM graphic.

It is helpful to see an example of project tracking that does not include earned value performance management. Consider a project that has been planned in detail, including a time-phased spend plan for all elements of work. Figure 1 shows the cumulative budget (cost) for this project as a function of time (the blue line, labeled PV). It also shows the cumulative actual cost of the project (red line) through week 8. To those unfamiliar with EVM, it might appear that this project was over budget through week 4 and then under budget from week 6 through week 8. However, what is missing from this chart is any understanding of how much work has been accomplished during the project. If the project were actually completed at week 8, then the project would actually be well under budget and well ahead of schedule. If, on the other hand, the project is only 10% complete at week 8, the project is significantly over budget and behind schedule. A method is needed to measure technical performance objectively and quantitatively, and that is what EVM accomplishes.

Project tracking with EVM

Consider the same project, except this time the project plan includes pre-defined methods of quantifying the accomplishment of work. At the end of each week, the project manager identifies every detailed element of work that has been completed, and sums the PV for each of these completed elements. Earned value may be accumulated monthly, weekly, or as progress is made.

Earned value (EV)

EV=StartCurrentPV(Completed)

Figure 2 shows the EV curve (in green) along with the PV curve from Figure 1. The chart indicates that technical performance (i.e., progress) started more rapidly than planned, but slowed significantly and fell behind schedule at week 7 and 8. This chart illustrates the schedule performance aspect of EVM. It is complementary to critical path or critical chain schedule management.

Figure 3 shows the same EV curve (green) with the actual cost data from Figure 1 (in red). It can be seen that the project was actually under budget, relative to the amount of work accomplished, since the start of the project. This is a much better conclusion than might be derived from Figure 1.

Figure 4 shows all three curves together – which is a typical EVM line chart. The best way to read these three-line charts is to identify the EV curve first, then compare it to PV (for schedule performance) and AC (for cost performance). It can be seen from this illustration that a true understanding of cost performance and schedule performance relies first on measuring technical performance objectively. This is the foundational principle of EVM.

Scaling EVM from simple to advanced implementations

The foundational principle of EVM, mentioned above, does not depend on the size or complexity of the project. However, the implementations of EVM can vary significantly depending on the circumstances. In many cases, organizations establish an all-or-nothing threshold; projects above the threshold require a full-featured (complex) EVM system and projects below the threshold are exempted. Another approach that is gaining favor is to scale EVM implementation according to the project at hand and skill level of the project team. [8] [9]

Simple implementations (emphasizing only technical performance)

There are many more small and simple projects than there are large and complex ones, yet historically only the largest and most complex have enjoyed the benefits of EVM. Still, lightweight implementations of EVM are achievable by any person who has basic spreadsheet skills. In fact, spreadsheet implementations are an excellent way to learn basic EVM skills.

The first step is to define the work. This is typically done in a hierarchical arrangement called a work breakdown structure (WBS) although the simplest projects may use a simple list of tasks. In either case, it is important that the WBS or list be comprehensive. It is also important that the elements be mutually exclusive, so that work is easily categorized in one and only one element of work. The most detailed elements of a WBS hierarchy (or the items in a list) are called activities (or tasks).

The second step is to assign a value, called planned value (PV), to each activity. For large projects, PV is almost always an allocation of the total project budget, and may be in units of currency (e.g., dollars or euros) or in labor hours, or both. However, in very simple projects, each activity may be assigned a weighted “point value" which might not be a budget number. Assigning weighted values and achieving consensus on all PV quantities yields an important benefit of EVM, because it exposes misunderstandings and miscommunications about the scope of the project, and resolving these differences should always occur as early as possible. Some terminal elements can not be known (planned) in great detail in advance, and that is expected, because they can be further refined at a later time.

The third step is to define “earning rules” for each activity. The simplest method is to apply just one earning rule, such as the 0/100 rule, to all activities. Using the 0/100 rule, no credit is earned for an element of work until it is finished. A related rule is called the 50/50 rule, which means 50% credit is earned when an element of work is started, and the remaining 50% is earned upon completion. Other fixed earning rules such as a 25/75 rule or 20/80 rule are gaining favor, because they assign more weight to finishing work than for starting it, but they also motivate the project team to identify when an element of work is started, which can improve awareness of work-in-progress. These simple earning rules work well for small or simple projects because generally each activity tends to be fairly short in duration.

These initial three steps define the minimal amount of planning for simplified EVM. The final step is to execute the project according to the plan and measure progress. When activities are started or finished, EV is accumulated according to the earning rule. This is typically done at regular intervals (e.g., weekly or monthly), but there is no reason why EV cannot be accumulated in near real-time, when work elements are started/completed. In fact, waiting to update EV only once per month (simply because that is when cost data are available) only detracts from a primary benefit of using EVM, which is to create a technical performance scoreboard for the project team.

Figure 5: A comparison of three EV curves without PV and AC.
Figure 5: A comparison of three EV curves without PV and AC.

In a lightweight implementation such as described here, the project manager has not accumulated cost nor defined a detailed project schedule network (i.e., using a critical path or critical chain methodology). While such omissions are inappropriate for managing large projects, they are a common and reasonable occurrence in many very small or simple projects. Any project can benefit from using EV alone as a real-time score of progress. One useful result of this very simple approach (without schedule models and actual cost accumulation) is to compare EV curves of similar projects, as illustrated in Figure 5. In this example, the progress of three residential construction projects are compared by aligning the starting dates. If these three home construction projects were measured with the same PV valuations, the relative schedule performance of the projects can be easily compared.

Intermediate implementations (integrating technical and schedule performance)

In many projects, schedule performance (completing the work on time) is equal in importance to technical performance. For example, some new product development projects place a high premium on finishing quickly. It is not that cost is unimportant, but finishing the work later than a competitor may cost a great deal more in lost market share. It is likely that these kinds of projects will not use the lightweight version of EVM described in the previous section, because there is no planned timescale for measuring schedule performance. A second layer of EVM skill can be very helpful in managing the schedule performance of these “intermediate” projects. The project manager may employ a critical path or critical chain to build a project schedule model. As in the lightweight implementation, the project manager must define the work comprehensively, typically in a WBS hierarchy. He/she will construct a project schedule model that describes the precedence links between elements of work. This schedule model can then be used to develop the PV curve (or baseline), as shown in Figure 2.

It should be noted that measuring schedule performance using EVM does not replace the need to understand schedule performance versus the project's schedule model (precedence network). However, EVM schedule performance, as illustrated in Figure 2 provides an additional indicator — one that can be communicated in a single chart. Although it is theoretically possible that detailed schedule analysis will yield different conclusions than broad schedule analysis, in practice there tends to be a high correlation between the two. Although EVM schedule measurements are not necessarily conclusive, they provide useful diagnostic information.

Although such intermediate implementations do not require units of currency (e.g., dollars), it is common practice to use budgeted dollars as the scale for PV and EV. It is also common practice to track labor hours in parallel with currency. The following EVM formulas are for schedule management, and do not require accumulation of actual cost (AC). This is important because it is common in small and intermediate size projects for true costs to be unknown or unavailable.

Schedule variance (SV)
SV=EVPV
SV greater than 0 is good (ahead of schedule). The SV will be 0 at project completion because then all of the planned values will have been earned.

However, Schedule Variance (SV) measured through EVM method is indicative only. To know whether a project is really behind or ahead of schedule (on time completion), Project Manager has to perform critical path analysis based on precedence and inter-dependencies of the project activities.

Schedule performance index (SPI)
SPI=EVPV
SPI greater than 1 is good (ahead of schedule).
See also earned schedule for a description of known limitations in SV and SPI formulas and an emerging practice for correcting these limitations.

Advanced implementations (integrating cost, schedule and technical performance)

In addition to managing technical and schedule performance, large and complex projects require that cost performance be monitored and reviewed at regular intervals. To measure cost performance, planned value (or BCWS - Budgeted Cost of Work Scheduled) and earned value (or BCWP - Budgeted Cost of Work Performed) must be in units of currency (the same units that actual costs are measured.) In large implementations, the planned value curve is commonly called a Performance Measurement Baseline (PMB) and may be arranged in control accounts, summary-level planning packages, planning packages and work packages. In large projects, establishing control accounts is the primary method of delegating responsibility and authority to various parts of the performing organization. Control accounts are cells of a responsibility assignment (RACI) matrix, which is the intersection of the project WBS and the organizational breakdown structure (OBS). Control accounts are assigned to Control Account Managers (CAMs). Large projects require more elaborate processes for controlling baseline revisions, more thorough integration with subcontractor EVM systems, and more elaborate management of procured materials.

In the United States, the primary standard for full-featured EVM systems is the ANSI/EIA-748A standard, published in May 1998 and reaffirmed in August 2002. The standard defines 32 criteria for full-featured EVM system compliance. As of the year 2007, a draft of ANSI/EIA-748B, a revision to the original is available from ANSI. Other countries have established similar standards.

In addition to using BCWS and BCWP, prior to 1998 implementations often use the term Actual Cost of Work Performed (ACWP) instead of AC. Additional acronyms and formulas include:

Budget at completion (BAC): The total planned value (PV or BCWS) at the end of the project. If a project has a Management Reserve (MR), it is typically not included in the BAC, and respectively, in the Performance Measurement Baseline.
Cost variance (CV)
CV=EVAC
CV greater than 0 is good (under budget).
Cost Performance Index (CPI)
CPI=EVAC
CPI greater than 1 is good (under budget):
< 1 means that the cost of completing the work is higher than planned (bad);
= 1 means that the cost of completing the work is right on plan (good);
> 1 means that the cost of completing the work is less than planned (good or sometimes bad).
Having a CPI that is very high (in some cases, very high is only 1.2) may mean that the plan was too conservative, and thus a very high number may in fact not be good, as the CPI is being measured against a poor baseline. Management or the customer may be upset with the planners as an overly conservative baseline ties up available funds for other purposes, and the baseline is also used for manpower planning.
Estimate at completion (EAC)
EAC is the manager's projection of total cost of the project at completion.
EAC=AC+(BACEV)CPI=BACCPI
This formula is based on the assumption, that the performance of the project (or rather a deviation of the actual performance from a baseline) to date gives a good indication of what a performance (of rather deviation of a performance from a baseline) will be in the future. In another words this formula is using statistics of the project to date to predict future results. Therefore it has to be used carefully, when the nature of the project in the future is likely to be different from the one to date (e.g. performance of the project compare to baseline at the design phase may not be a good indication of what it will be during a construction phase).
Estimate to complete (ETC)
ETC is the estimate to complete the remaining work of the project.
ETC=EACAC
To-complete performance index (TCPI)
The TCPI provides a projection of the anticipated performance required to achieve either the BAC or the EAC. TCPI indicates the future required cost efficiency needed to achieve a target BAC (Budget At Complete) or EAC (Estimate At Complete). Any significant difference between CPI, the cost performance to date, and the TCPI, the cost performance needed to meet the BAC or the EAC, should be accounted for by management in their forecast of the final cost.
For the TCPI based on BAC (describing the performance required to meet the original BAC budgeted total):
TCPIBAC=BACEVBACAC
or for the TCPI based on EAC (describing the performance required to meet a new, revised budget total EAC):
TCPIEAC=BACEVEACAC
This implies, that if revised budget (EAC) is calculated using Earned Value methodology formula (BAC/CPI), then at the moment, when TCPI based on EAC is first time calculated, it will always be equal to CPI of a project at that moment. This happens because when EAC is calculated using formula BAC/CPI it is assumed, that cost performance of the remaining part of the project will be the same as the cost performance of the project to date.
Independent estimate at completion (IEAC)
The IEAC is a metric to project total cost using the performance to date to project overall performance. This can be compared to the EAC, which is the manager's projection.
IEAC=AC+(BACEV)CPI

Agile EVM

In complex environments like software development, an iterative and incremental or Agile approach is often used to deliver complex products more successfully. Agile EVM is used as trend burndown/burnup graphs to make forecasts of progress towards a completion date transparent. However, EVM techniques are always used for the underlying calculations.

Preparation

Setting up Agile EVM is similar to a simple implementation of EVM with the following preparation steps:

  1. All project work is gathered as work items (i.e. Stories or Requirements) and managed in a single ordered list (i.e. Prioritized Requirements List or Product Backlog);
  2. Planned Value is determined by estimating the relative size of a work item compared to other items. Story Points are used as the unit of measurement for PV and EV;
  3. The one, and only, earning rule is that when a work item is done then the corresponding Story Points for a work item are earned. To agree what "done" means, project teams establish and share a Definition of Done, listing all criteria a work item has to comply with before it's considered done. To mitigate project risks no partially done work items are ever considered.

Practices

Figure 6: Release Burndown Chart for Agile EVM with scope increase using the Agile Compass.[10]

Agile EVM is now all about executing the project and tracking the accumulated EV according to the simple earning rule. Because Agile EVM has been evolving for many years the following practices are well-established:

  • EV is accumulated at fixed time intervals (i.e. Timebox, Iteration or Sprint) of 1–4 weeks;
  • PV and EV is graphically tracked & extrapolated as remaining value in a Release Burndown Chart as shown in figure 6;
  • Rather than a S-shaped curve the PV in Agile EVM is a straight line because an Agile project has no distinct phases and corresponding variances in the rate of value delivery;
  • The EV in Story Points done in one fixed time interval is known as the Velocity of a team;
  • In Agile scope change is embraced and the amount of added (removed) scope in Story Points is added (removed) to the Velocity or Scope Floor. The latter is shown in Figure 6 where several scope increases have lowered the Scope Floor below the x-axis. The advantage of using a Scope Floor is that any scope changes can easily be separated from Velocity variances;
  • The intersection between the Remaining Value and Scope Floor lines indicates the expected release date and the corresponding Remaining Budget.

Calculations

Agile EVM is based on transparency and therefore graphically used in various trend charts. However, all EVM formulas (CPI, SPI, EAC, etc.) can still be used in Agile EVM by expressing the input variables like EV, PV and AC as:

  • Percentages of the number of planned or earned Story Points of the total number of Story Points or;
  • Financials by distributing the project budget over the total number of Story Points.

Agile embraces change and therefore scope is considered variable (i.e. not fixed). Instead of using the INITIAL estimate in total number of Story Points, in Agile EVM calculations always the LATEST estimate in total number of Story Points is used to calculate CPI, SPI, EAC, etc.

Schedule Performance

The use of SPI in EVM is rather limited in forecasting schedule performance problems because it is dependent on the completion of earned value on the Critical Time Path(CTP).

Because Agile EVM is used in a complex environment, any earned value is more likely to be on the CTP. The latest estimate for the number of fixed time intervals can be calculated in Agile EVM as:

  • Initial Duration in number of fixed time intervals / SPI or;
  • Latest Estimate in total number of Story Points / Velocity.

Limitations

Proponents of EVM note a number of issues with implementing it[11] ,[12] and further limitations may be inherent to the concept itself.

EVM has no provision to measure project quality, so it is possible for EVM to indicate a project is under budget, ahead of schedule and scope fully executed, but still have unhappy clients and ultimately unsuccessful results. One solution for including a quality metric in EVM is to validate/verify what percentage of the requirements (including customer requirements for quality) each 'work' element meets. A work element's %EV is then correlated with that %completion of requirements. For example a complex software routine might meet 75% of its requirements and therefore be counted at 75% EV.

Because EVM requires quantification of a project plan, it is often perceived to be inapplicable to discovery-driven or Agile software development projects. For example, it may be impossible to plan certain research projects far in advance, because research itself uncovers some opportunities (research paths) and actively eliminates others. However, another school of thought holds that all work can be planned, even if in weekly timeboxes or other short increments. Thus, the challenge is to create agile or discovery-driven implementations of the EVM principle, and not simply to reject the notion of measuring technical performance objectively. (See the lightweight implementation for small projects, described above). Applying EVM in fast-changing work environments is, in fact, an area of project management research.[13]

Traditional EVM is not intended for non-discrete (continuous) effort. In traditional EVM standards, non-discrete effort is called “level of effort" (LOE). If a project plan contains a significant portion of LOE, and the LOE is intermixed with discrete effort, EVM results will be contaminated.[14] This is another area of EVM research.

Traditional definitions of EVM typically assume that project accounting and project network schedule management are prerequisites to achieving any benefit from EVM. Many small projects don't satisfy either of these prerequisites, but they too can benefit from EVM, as described for simple implementations, above. Other projects can be planned with a project network, but do not have access to true and timely actual cost data. In practice, the collection of true and timely actual cost data can be the most difficult aspect of EVM. Such projects can benefit from EVM, as described for intermediate implementations, above, and Earned Schedule.

As a means of overcoming objections to EVM's lack of connection to qualitative performance issues, the Naval Air Systems Command (NAVAIR) PEO(A) organization initiated a project in the late 1990s to integrate true technical achievement into EVM projections by utilizing risk profiles. These risk profiles anticipate opportunities that may be revealed and possibly be exploited as development and testing proceeds. The published research resulted in a Technical Performance Management (TPM) methodology and software application that is still used by many DoD agencies in informing EVM estimates with technical achievement.[15] The research was peer-reviewed and was the recipient of the Defense Acquisition University Acquisition Research Symposium 1997 Acker Award for excellence in the exchange of information in the field of acquisition research.

There is the difficulty inherent for any periodic monitoring of synchronizing data timing: actual deliveries, actual invoicing, and the date the EVM analysis is done are all independent, so that some items have arrived but their invoicing has not and by the time analysis is delivered the data will likely be weeks behind events. This may limit EVM to a less tactical or less definitive role where use is combined with other forms to explain why or add recent news and manage future expectations.

There is a measurement limitation for how precisely EVM can be used, stemming from classic conflict between accuracy and precision, as the mathematics can calculate deceptively far beyond the preciseness of the measurements of data and the approximation that is the plan estimation. The limitations on estimation is commonly understood (such as the ninety-ninety rule in software) but is not visible in any margin of error. The limitations on measurement are largely a form of digitization error as EVM measurements ultimately can be no finer than by item, which may be the Work Breakdown Structure terminal element size, to the scale of reporting period, typically end summary of a month, and by the means of delivery measure. (The delivery measure may be actual deliveries, may include estimates of partial work done at the end of month subject to estimation limits, and typically does not include QC check or risk offsets.)

See also

References

43 year old Petroleum Engineer Harry from Deep River, usually spends time with hobbies and interests like renting movies, property developers in singapore new condominium and vehicle racing. Constantly enjoys going to destinations like Camino Real de Tierra Adentro.

Further reading

  • Humphreys, Gary (2001). Project Management Using Earned Value. Humphreys and Associates. ISBN 0-9708614-0-0
  • Philipson, Erik and Sven Antvik (2009). Earned Value Management - an introduction. Philipson Biz. ISBN 978-91-977394-5-0
  • Project Management Institute (2005). Practice Standard for Earned Value Management. Project Management Institute. ISBN 1-930699-42-5
  • Solomon, Paul and Ralph Young (2006). Performance-Based Earned Value. Wiley-IEEE Computer Society. ISBN 978-0-471-72188-8
  • Stratton, Ray (2006). The Earned Value Maturity Model. Management Concepts. ISBN 1-56726-180-9
  • U.S. Air Force Materiel Command (1994). "Guide to Analysis of Contractor Cost Data". AFMCPAM 65-501
  • Defense Contract Management Agency (2006) "Earned Value Implementation Guide" DAU link ISBN 978-1468178289
  1. Marshall, Robert. The Contribution of Earned Value Management to Project Success of Contracted Efforts. Journal of Contract Management, 2007, pp. 21-331.
  2. Template:Cite news
  3. Template:Cite news
  4. Template:Cite news
  5. See also:
  6. Template:Cite web Template:Dead link
  7. Template:Cite web
  8. Template:Cite web
  9. 20 year-old Real Estate Agent Rusty from Saint-Paul, has hobbies and interests which includes monopoly, property developers in singapore and poker. Will soon undertake a contiki trip that may include going to the Lower Valley of the Omo.

    My blog: http://www.primaboinca.com/view_profile.php?userid=5889534
  10. Template:Cite web
  11. Template:Cite web
  12. Template:Cite web
  13. Template:Cite web Template:Dead link
  14. Template:Cite web
  15. Template:Cite web